Commissioning
6.1
General requirements
Before commissioning it must be checked that:
● The device has been installed and connected in accordance with the guidelines provided
in chapter 4 "Installing/mounting (Page 31)" and chapter 5 "Connecting (Page 35)"
● Device installed in hazardous location meets the requirements described in "Installation in
hazardous location (Page 14)"
Commissioning
Note
Refer to Programming the Transmitter (Page 49) if needed.
1. Scroll down to [Install Sensor] and press <Right Arrow>.
2. Scroll down to [Install Complete]. Press the <Right Arrow> and select [Install]. Press
<ENTER>. The flow meter will go through its drives.
FUE1010 IP65 NEMA 4X
Operating Instructions, 12/2014, A5E03086491-AC
6
87