Installing the Device
Figure 9: Wall Mounting the Server
Powering On the Server
1. Attach the power cord to the power supply unit in the server and then attach the other end of the power
chord to the grounded power outlet.
2. Wait for approximately three minutes.
3. Verify the power status of the system by looking at the system power status LED. The power status LED
blinks in amber color during initial boot up and in solid amber when the system reaches the standby power
mode.
Initial Server Setup
Local Connection Procedure
1. Ensure that the device is powered on.
Cisco 5400 Enterprise Network Compute System Hardware Installation Guide
Powering On the Server
27