802-9074.9 • INSTALLATION AND OPERATING INSTRUCTIONS • NXPLUS C Wind • Revision 05
12
Before installation
12.1
Preliminary clarifications
In order to load the transport units in a suitable installation order, the regional Siemens
representative requires the following information from you several weeks before delivering the
switchgear:
• Sketch of the installation room including the locations and numbers of the individual panels
and the storage space for the accessories
• Sketch of the access route from the public road to the switchgear building and information
concerning the condition thereof (meadows, arable soil, sand, gravel, etc.)
• Sketch of the transport route inside the switchgear building with the locations and
dimensions of doors and other narrow points, as well as the floor number of the installation
room
• Information about available lifting equipment, e.g. mobile crane, fork-lift truck, lifting truck,
hydraulic jack, roller pads. If no lifting equipment is available, please notify this explicitly
12.2
Intermediate storage
DANGER!
Risk of injury and damage to the storage place and the stored goods if the storage space is
overloaded.
Observe the load-bearing capacity of the floor.
Do not stack the transport units.
Do not overload lighter components by stacking.
ATTENTION!
Fire risk. The transport unit is packed in flammable materials.
No smoking.
Keep fire extinguishers in a weatherproof place.
Mark the location of the fire extinguisher.
ATTENTION!
Supplied desiccant bags lose their effectiveness if they are not stored in the undamaged
original packings.
Do not damage or remove packing of desiccant bags.
Do not unpack desiccant bags before use.
If the comprehensive accessories, the delivered switchgear or parts thereof have to be stored
before installation, a suitable storage room or place has to be selected and prepared.
Intermediate storage of the transport units:
• In original packing as far as possible
• Permissible storage temperature of the primary part from -40° C to +70° C or in accordance
with the permissible storage temperatures of the installed secondary devices
• In a weatherproof place
• Protected against damage
• If packed in seaworthy crates, the switchgear can be stored for a maximum of 6 months
(desiccant bags)
• Store transport units in such a way that they can be taken out later in the correct order for
installation.