Site Preparation Checklist
Table 2-2
Site Planning Checklist
Task No.
Planning Activity
1
Space evaluation:
Space and layout
Floor covering
Impact and vibration
Lighting
Maintenance access
2
Environmental evaluation:
Ambient temperature
Humidity
Altitude
Atmospheric contamination
Airflow
3
Power evaluation:
Input power type
Power receptacles (Depends on power supply)
Receptacle proximity to the equipment
Dedicated (separate) circuits for redundant
power supplies
UPS for power failures
DC systems: Proper gauge wire and lugs
4
Grounding evaluation:
Circuit breaker size
CO ground (AC- and DC-powered systems)
5
Cable and interface equipment evaluation:
Cable type
Connector type
Cable distance limitations
Interface equipment (transceivers)
6
EMI evaluation:
Distance limitations for signaling
Site wiring
RFI levels
1. Verify that each power supply installed in the chassis has a dedicated AC source or DC source circuit.
2. Refer to the power supply's kVA rating as a sizing criteria in determining the output required by the UPS. The power supply's
kVA rating value is listed in the specifications table for each power supply in Appendix A.
Catalyst 4948E and Catalyst 4948E-F Switch Installation Guide
2-14
Verified By Time
1
2
Chapter 2
Preparing for Installation
Date
OL-21561-02