Note: 1) At outdoor application, the using of protective cover (option code H00) is recommended; 2) At out door application the protection of shaft again jet-water is recommended; 2.0 HANDLING AND STORAGE When lifting the motors, always use the lifting eyes provided or machines may only be hoisted in a position corresponding to their basic type of construction.
The service life of the motor can be considerably reduced if the storage period extends beyond 2 years in environments with high moisture and dirt. If necessary, the insulation resistance of the winding could be measured determine the health of the motor prior to installation and start-up, (see Section 3.5.
3.1.2 Installation requirement Because of the manufacture tolerance and cumulate errors existing in mechanical parts, clearance may exist between the motor feet plane and the foundation support surface. When install motors, the clearance size must be measured carefully by feeler gauge. For clearance which >0.05mm, shim with proper thickness should be inserted.
3.4 Electrical connection All work must be carried out by skilled worker. Before starting any work, be sure to isolate the machine from the main and auxiliary power supply as applicable. Mains must be secured against accidental switch on. There are six power supply terminals and two earthing positions located in the terminal box. There is an earthing point located on the base of the frame.
Page 21
Star connection A star connection is obtained by connecting W2, U2, V2 terminals to each other and the U1, V1, W1 terminals to the mains. U2 (V2, W2) Delta connection A delta connection is obtained by connecting the end of a phase to the beginning of the next phase.
Insulation resistance The minimum insulation resistance between new, cleaned or repaired windings with reference to ground is 10 M . The critical insulation resistance (Recruit) is calculated by multiplying the rated voltage, e.g. 0.69 kV AC, with the constant factor (0.5M / kV): Recruit = 0.69 kV×0.5 M /kV = 0.345 M Measurement...
Electromagnetic compatibility In application where the motor is driven by a drive, the degree of electrical interference depends on the type of used drive (type, number of IGBTs, interference suppression measures, and manufacturer), cabling, distance and application requirements. The installation guidelines of the drive manufacturer with regards to electromagnetic compatibility must be considered at all times during the design and implementation phases.
It is recommended that the DE and NDE bearings should be re-greased while the motor is in operating and at operating temperature. If it is not possible to re-grease the motor during operation, then it recommended that a partial amount of the grease is injected and then the motor energized and rotated for a few revolutions to allow for grease dispersion.
4.6 Condensation drain plug Based on the motor's construction and mounting type, please consider to select the drainage hole option (option code H03). Drainage hole is on motor's frame, and it is closed by a plastic plug when delivered. 5.0 START UP Preliminary Inspection Before applying power to the motor for the first time, it is recommended to check: 1) All retaining bolts are tightened including transmission coupling and alignment...