UPS5000-H-(1200 kVA-1600 kVA) Quick Guide (100 kVA Power Modules, Three-Phase Three-Wire)
01
Installation Preparations
1. Before installation, read the user manual carefully to get familiar with product information and safety precautions.
2. Use insulated tools when installing the equipment.
3. Only engineers certified by Huawei or its agent are allowed to install, commission, and maintain the UPS. Otherwise,
personal injury or equipment damage may occur, and the resulting UPS faults are beyond the warranty scope of Huawei.
4. This document describes the installation procedure for a single UPS. For details about how to install a parallel system,
contact Huawei technical support.
Model
Weight
UPS5000-H-1200K-NTN
< 1600 kg
UPS5000-H-1600K-NTN
< 2300 kg
Inductor cabinet
< 1100 kg
Clearances and Cabinet Description (1200 kVA)
Cabinet Description
SPDs and
SPD switches
Power modules
Dimensions (H x W x D)
2200 mm x 1600 mm x 1000 mm
2200 mm x 2400 mm x 1000 mm
2000 mm x 600 mm x 1000 mm
Installation
Clearances
UPS cabinet
Rectifiers
Surge protection boxes
Control module
Main switch QF of the inductor cabinet
Bypass fan power supply unit (PSU)
Intelligent detection card
Bypass modules
Fan power switch QS1-4
Bypass control module
Fans
Item
Mains input
Mains input current (A)
Bypass input
Bypass input current (A)
Output
Output current (A)
Nominal battery discharge current (A)
Battery input (lead-acid
Maximum battery discharge current (A)
battery)
Recommended cross-sectional area
(mm
2
)
Nominal battery discharge current (A)
Maximum battery discharge current (A)
Battery input (SmartLi)
Recommended cross-sectional area (mm
Equipotential ground point Recommended cross-sectional area (mm
Clearances and Cabinet Description (1600 kVA)
Inductor
cabinet
Cabinet Description
SPDs and
SPD switches
Power modules
1
Issue: 01
Date: 2021-10-13
1200 kVA
1600 kVA
Remarks
2229
2972
Connection method: Crimped DT terminal
1823
2431
Bolt specifications:
1823
2431
L1/L2/L3/U/V/W/PE: M12 x 45 mm (47 N· m)
2660
3546
Battery +/-/PE: M16 x 55 mm (120 N· m)
3185
4247
Equipotential ground point: M6 x 20 mm (4.5 N· m)
+/-
6 x (2 x 240)
8 x (2 x 240)
NOTE:
PE
2 x 240
•
The currents listed in the table are measured at a rated voltage
2493
3324
of 380 V.
3192
4172
•
If the top cabling component and bottom cabling cabinet are
For details, see the IEC-60364-5-52
not configured, copper bars need to be prepared for the mains
2
)
specifications and
SmartLi User Manual
.
input, bypass input, and output, which cannot be directly
connected using cables. (Huawei does not provide copper bars
or connector boxes.) If they are configured, refer to the
2
) 16
recommended cable specifications in the user manual.
•
The battery input can be connected only using cables.
Installation
Clearances
Power
cabinet 1
Inductor
Power
cabinet
cabinet 2
Bypass
cabinet
Rectifiers
Surge protection boxes
Main switch QF of the
inductor cabinet
Control module
Intelligent detection card
Bypass fan PSU
Fan power switch QS1-4
Bypass modules
Bypass control module
Fans