Install Expansion Modules (Optional)
Cable the Switch
If the brackets do not slide easily, the alignment may be off. Pull the switch back toward you and
realign the brackets.
Figure 1-5: Sliding the Switch Into the Rack
8.
Secure the switch with your screws through the front of the rack, as show in
Figure 1-6: Secure Switch with Screws through the Front of the Rack
1.
Install any optional Fibre Channel or Ethernet Gateway modules.
2.
Install all hardware components before the Topspin 90 is powered on.
3.
A gateway module or blanking panel must always be installed.
Connect Management Ports
1.
Connect one end of the RJ-45 console cable to the InfiniBand chassis serial console port.
2.
Connect the other end of the serial cable to your terminal server or management workstation.
3.
Connect an Ethernet cable to the Ethernet port (bottom port).
4.
Check the LEDs on the Management ports. The link status should be lit.
5
Figure
1-6.