Chapter 3
Installing the Switch
Verifying Switch Operation
Step 1
Step 2
Step 3
Step 4
Step 5
Step 6
78-6286-05
Figure 3-16 Ethernet Cable with RJ-45 Connector
After you have connected all the interfaces, check all connections, and then
perform the following steps to power on the system to verify that it is operational:
Before powering on the system, make sure the connector is installed securely in a
grounded outlet at the power-source end of the power cord and that the source
power is within the range labeled on the back of the switch. When two power
supplies are present, make sure that the second cord is connected to a separate line
from the first, if possible.
Check the console terminal and make sure it is powered on.
Connect the power cords to the switch.
Verify that the PSI or PWR LEDs on the power supply front panel is green.
Listen for the system fans to ensure that they are operational.
While the system initializes, check that the STATUS LED on the supervisor
engine is amber until the boot is complete.
Many of the interface LEDs do not illuminate until you configure the
Note
interfaces.
When the system boot is complete (it takes a few seconds), the supervisor engine
begins to initialize the interfaces. During this initialization, the interface LEDs
flash on and off. When initialization is complete, the console screen displays a
script and system banner.
Catalyst 2984G, 2948G-GE-TX, and 2980G Switch Hardware Installation Guide
Verifying Switch Operation
3-23