hit counter script
Honeywell NOTIFIER INSPIRE E10 Commissioning Instructions

Honeywell NOTIFIER INSPIRE E10 Commissioning Instructions

Fire alarm control panels
Hide thumbs Also See for NOTIFIER INSPIRE E10:

Advertisement

Quick Links

Notifier INSPIRE E10/E15
Fire Alarm Control Panels
Commissioning
Instructions

Advertisement

Table of Contents
loading

Summary of Contents for Honeywell NOTIFIER INSPIRE E10

  • Page 1 Notifier INSPIRE E10/E15 Fire Alarm Control Panels Commissioning Instructions...
  • Page 2: Table Of Contents

    CONTENTS Related Documents Conventions Introduction Commissioning Preliminary Checks Sensors and Modules checks Loop Wiring Tests POL 200 tool To perform loop wiring checks, Using a Multimeter: Connecting the opal/clip loop wiring to the panel Initial Power Up Device Loop wiring and Checks RS485 Cable check Other External Wiring Configuration and System Test...
  • Page 3 Notifier INSPIRE E10/E15 Control Panels - Commissioning Disablement Events Alarm Events...
  • Page 4: Related Documents

    RELATED DOCUMENTS ABBREVIATIONS This guide does not describe any of the panel operating and Control and Indicating Equipment installation instructions, refer to: Central Processing Unit INSPIRE E10/E15 Control Panel Operating Manual (Part Smaller 10U size Panel enclosure † number HOP-338-9EN) Larger 15U size Panel enclosure INSPIRE E10/E15 Control Panel Installation Manual Electromagnetic compatibility...
  • Page 5: Introduction

    Notifier INSPIRE E10/E15 Control Panels - Commissioning Introduction The purpose of this manual is to provide the user with recommendations on procedure for Commissioning of INSPIRE Fire Alarm Control Panel based Fire Control System.
  • Page 6: Commissioning

    Commissioning To bring the Notifier INSPIRE E10/E15 Control panel into an operational state ready for configuration, follow the steps detailed below. Information on how to configure the panel is given in the Notifier INSPIRE E10/E15 Control Panel Configuration Tool Manual.
  • Page 7 Notifier INSPIRE E10/E15 Control Panels - Commissioning Ensure Modules are installed into their allowed slot locations It is required that the Charger module is always fitted in Slot 1 of the module carrier and CPU Module fitted in Slot 2 of Module Carrier.
  • Page 8: Sensors And Modules Checks

    The Notifier INSPIRE E10/E15 Control panel Dual Loop module Opal (HOP-433-100) has the capacity to allows connection of up to 318 loop OPAL devices per analogue loop, consisting of up to 159 detectors and 159 modules.
  • Page 9: Loop Wiring Tests

    Notifier INSPIRE E10/E15 Control Panels - Commissioning LOOP WIRING TESTS Refer to the module installation instructions to identify the terminals for cable connections. NEVER use a high-voltage tester on the detection loop. Once any loop devices are connected, no high-voltage testers, such as Megger may be used on the loop circuit;...
  • Page 10 Commissioning Typical connections of addressable devices to a loop are shown below: Loop Input Loop Input 2 Input 1 Output Interface Manual Call Point 1 2 3 4 5 6 7 8 9 10 1 Loop 1 OUT +VE Detector 2 Loop 1 OUT VE 6 Loop 2 OUT +VE 7 Loop 2 OUT VE...
  • Page 11: Pol 200 Tool

    Notifier INSPIRE E10/E15 Control Panels - Commissioning POL 200 TOOL If available use the POL-200-TS tool to check and test loop circuits. POL200 tool can be used to capture more detailed diagnostics as it works in both Opal and Clip protocols.
  • Page 12: Connecting The Opal/Clip Loop Wiring To The Panel

    Commissioning after the links in the isolators have been removed and the system has been configured). Use a meter to check that there are no connections between each cable screen and: the +ve conductor of the cable the -ve conductor of the cable. Note: It is recommended that the cable screen is earthed at the panel.
  • Page 13: Initial Power Up

    Notifier INSPIRE E10/E15 Control Panels - Commissioning INITIAL POWER UP The Panel must only be powered up initially without the external wiring connected. Ensure adequate precautions are taken to safe guard against inadvertent switching on of power to the panel and to the associated system equipment during commissioning.
  • Page 14: Other External Wiring

    Commissioning OTHER EXTERNAL WIRING Refer to the appropriate module wiring instructions to identify the terminals for cable connections. Commissioning the external wiring comprises the following main steps: Check the module external wiring for continuity, short circuits and open circuits. Connect the external wiring to the panel. Check for faults after the external wiring is connected to the powered-up panel.
  • Page 15 Notifier INSPIRE E10/E15 Control Panels - Commissioning Module firmware upgrade USB METHOD OF MODULE SOFTWARE UPGRADE You will need a blank memory stick, access to module software image and panel access level 2 PIN. Format USB Stick with volume label HONEYWELL...
  • Page 16: Configuration And System Test

    Configuration and System Test Configuration and System Test CONFIGURATION TOOL The GLSS Notifier INSPIRE Configuration tool must be used to configure a an INSPIRE Fire detection and alarm system to site specific requirements and to national and local regulations. Once a system is configured the Configuration tool must be connected to an INSPIRE panel and system synchronised.
  • Page 17: Maintenance

    Notifier INSPIRE E10/E15 Control Panels - Commissioning Maintenance A log book should be used for recording day to day events in the system, it should be used to record service and maintenance work visits. ROUTINE TESTING In order to ensure that the system is fully operational it must be routinely tested in accordance with the requirements of EN54-14, national code of practice and local requirements.
  • Page 18: Messages And Their Meanings

    Messages and their Meanings Messages and their Meanings The list of messages shown below are of Fault, Disablement and some Status displayed at an INSPIRE panel. Messages are categorised, with meaning and possible action information to remedy the condition where appropriate.
  • Page 19: Fault Events

    Notifier INSPIRE E10/E15 Control Panels - Commissioning Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. FAULT EVENTS...
  • Page 20: Processor Related Faults

    Messages and their Meanings Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. NO CONFIRMATION SIGNAL RECEIVED Confirmation signal not received within time limit. Action: TBA.
  • Page 21: Configuration Related Faults

    Notifier INSPIRE E10/E15 Control Panels - Commissioning Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. FIRMWARE IS LOADING Firmware update is happening.
  • Page 22: Psu & Charger Related Faults

    Messages and their Meanings Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. CONFIGURATION IS LOADING Configuration is loading. Action: Wait for configuration to be fully loaded.
  • Page 23 Notifier INSPIRE E10/E15 Control Panels - Commissioning Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. BATTERY HIGH RESISTANCE Battery with high resistance has been detected.
  • Page 24 Messages and their Meanings Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. CHARGER FAULT A charger fault has been detected. Action: Check Charger module is corrected seated and check internal wiring of PSU, Charger module and batteries.
  • Page 25 Notifier INSPIRE E10/E15 Control Panels - Commissioning Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. EXTERNAL POWER SUPPLY FAULT External power supply has a fault.
  • Page 26 Messages and their Meanings Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. POWER SUPPLY OUTPUT FAULT The output from the PSU has a fault. Action: Check the PSU wiring connections and its output voltage and local indications.
  • Page 27: Wiring & Driver Related Faults

    Notifier INSPIRE E10/E15 Control Panels - Commissioning Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. WIRING & DRIVER RELATED FAULTS...
  • Page 28 Messages and their Meanings Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. OPEN CIRCUIT ON POSTIVE LINE An open circuit has been detected on the positive line of loop wiring.
  • Page 29: Communication & Mapping Faults

    Notifier INSPIRE E10/E15 Control Panels - Commissioning Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. COMMUNICATION & MAPPING FAULTS COMMUNICATION ERROR OR TRANSMISSION Communication error or transmission fault detected.
  • Page 30 Messages and their Meanings Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. HIGH COMMUNICATION ERROR RATE High communication error rate detected. Action: Seek help, contact Notifier technical support.
  • Page 31 Notifier INSPIRE E10/E15 Control Panels - Commissioning Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. NO REPLY The panel is no longer able to communicate with a device.
  • Page 32: Field Device Faults

    Messages and their Meanings Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. FIELD DEVICE FAULTS ASPIRATION CONFIGURATION FAULT Aspiration configuration fault has been detected.
  • Page 33 Notifier INSPIRE E10/E15 Control Panels - Commissioning Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. ASPIRATION LOW FLOW Aspiration low flow fault detected.
  • Page 34 Messages and their Meanings Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. BEAM BLOCKED Check the line of sight between the beam transmitter and the reflector for a blockage in the beam path.
  • Page 35 Notifier INSPIRE E10/E15 Control Panels - Commissioning Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. BEAM LOCAL TEST FAILED Beam panel local test has failed.
  • Page 36 Messages and their Meanings Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. CO SENSOR FAULT CO sensor fault detected. Action: Replace the device.
  • Page 37 Notifier INSPIRE E10/E15 Control Panels - Commissioning Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. IR SATURATION The sensor is dirty or is located where too much ambient light is penetrating the sensor’s detection...
  • Page 38 Messages and their Meanings Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. SPEECH CIRCUIT FAULT Speech circuit fault detected. Action: TBA STROBE CIRCUIT FAULT Strobe circuit fault detected.
  • Page 39: Maintenance Events

    Notifier INSPIRE E10/E15 Control Panels - Commissioning Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. MAINTENANCE EVENTS BATTERY LIFE WARNING Warning for end of battery life.
  • Page 40: Test Operation Messages

    Messages and their Meanings Message Meaning and possible remedial action. If a fault persists then seek advice. Any remedial action requiring wiring or replacement of parts, this work must be done by a trained engineer. TEST OPERATION MESSAGES FARE REMOVED FROM TEST A message to inform that Fire Alarm Routing Equipment has been removed from Test mode.
  • Page 41 Notifier INSPIRE E10/E15 Control Panels - Commissioning DISABLEMENT EVENTS DISABLED A part of the system such as a Detection Zone, Loop Device, Alarm Zone, Control Zone, FARE or FRE is disabled and the disablement action was successful. Action: Re-enable the disablement when required.
  • Page 42 Messages and their Meanings ALARM EVENTS ALARM Indicates an Alarm has been reported from a detection device. PRE ALARM Certain detection device types has the ability to report when an alarm has been almost reached but not fully, which is called pre alarm. Note a pre alarm in time can go into a full alarm.
  • Page 43 Notifier INSPIRE E10/E15 Control Panels - Commissioning...
  • Page 44 Do not dispose of with your normal household waste. Do not burn. Notifier by Honeywell reserves the right to revise this publication from time to time and make changes to the content hereof without obligation to notify any person of such revisions of changes.

This manual is also suitable for:

Notifier inspire e15

Table of Contents