Air Flow Guidelines; Method Of Procedure - Cisco ASR 901 10G Series Hardware Installation Manual

Aggregation services router
Table of Contents

Advertisement

Chapter 2
Preparing to Install the Router
For an outside plant installation (cell site cabinet, hut, etc.), it is required that the router be protected
Note
against airborne contaminants, dust, moisture, insects, pests, corrosive gases, polluted air or other
reactive elements present in the outside air. To achieve this level of protection, it is recommended that
the unit is installed in a fully sealed (i.e. Closed Loop) enclosure. Examples of such cabinets include
IP65 cabinets with heat exchanger, complying with Telecordia GR487.

Air Flow Guidelines

To ensure adequate air flow through the equipment rack, we recommend that you maintain a clearance
of at least 6 inches (15.24 cm) on each side of the rack at all times.
If air flow through the equipment rack and the routers that occupy it is blocked or restricted, or if the
Caution
ambient air being drawn into the rack is too warm, an over temperature condition can occur within the
rack and the routers that occupy it.
The site should also be as dust-free as possible. Dust tends to clog the router fans, reducing the flow of
cooling air through the equipment rack and the routers. Thus, increasing the risk of an over temperature
condition.
Use the following guidelines to plan your equipment rack configuration:

Method of Procedure

Part of site preparation includes reviewing installation plans or method of procedures (MOPs). An
example of a MOP that includes pre-installation checklist of tasks, considerations to address and agree
upon before proceeding with the installation, is as follows:
1.
2.
3.
4.
5.
OL-28105-02
5% to 85% RH
Mount the Cisco ASR 901 10G router in a 19-inch rack (with a 17.5- or 17.75-inch opening).
Beside air flow, you must allow clearance around the rack for maintenance.
Enclosed racks must have adequate ventilation. Ensure that the rack is not congested, because each
router generates heat. An enclosed rack should have louvered sides and a fan to provide cooling air.
Heat that is generated by equipment near the bottom of the rack can be drawn upward into the intake
ports of the equipment above.
When mounting a chassis in an open rack, ensure that the rack frame does not block the intakes or
(on the left side of the chassis) or the exhaust (on the right side of the chassis).
When a rack-installed equipment fails, especially equipment in an enclosed rack, try making the
equipment operate by itself, if possible. Power off other equipment in the rack (and in adjacent
racks) to give the router a maximum of cooling air and clean power.
Read this hardware installation guide.
Assign personnel.
Determine protection requirements for personnel, equipment, and tools.
Evaluate potential hazards that may affect service.
Schedule time for installation.
Cisco ASR 901 10G Series Aggregation Services Router Hardware Installation Guide
Site Planning
2-5