Summary of Contents for GE Masoneilan 10000 Series

  • Page 1 GE Oil & Gas 10000 Series Masoneilan* Double Ported Globe Valve Instruction Manual GE Data Classification : Public...
  • Page 2 SPECIFIC REFERENCE INFORMATION IN ADDITION TO THE CUSTOMER/OPERATOR’S NORMAL OPERATION AND MAINTENANCE PROCEDURES. SINCE OPERATION AND MAINTENANCE PHILOSOPHIES VARY, GE (GENERAL ELECTRIC COMPANY AND ITS SUBSIDIARIES AND AFFILIATES) DOES NOT ATTEMPT TO DICTATE SPECIFIC PROCEDURES, BUT TO PROVIDE BASIC LIMITATIONS AND REQUIREMENTS CREATED BY THE TYPE OF EQUIPMENT PROVIDED.
  • Page 3: Table Of Contents

    6.4 Plug Stem Pinning .............................4 6.5 Packing Box ................................5 6.6 Packing Box (Optional Lubrication Figure 7) ..................5 7. Valve Body Reassembly ......................... 6 © 2015 General Electric Company. All rights reserved. Masoneilan 10000 Series Globe Valve Instruction Manual | c...
  • Page 4 GE recommended usages. GE reserves the right to discontinue Indicates a potentially hazardous situation which, if not avoided, manufacture of any product or change product materials, design could result in death or serious injury.
  • Page 5: Introduction

    These installation and maintenance instructions apply 3.3 The valve must be installed so that the control substance to all sizes and ratings of the Masoneilan 10000 Series control will flow through the valve body in the direction indicated by valves, regardless of the type of trim used.
  • Page 6: Body Disassembly (Refer To Figure 9)

    If a short period of lapping does not visibly improve seating there is usually no advantage in continuing, as too much lapping may result in rough seats. The only remedy is 3 | GE Oil & Gas © 2015 General Electric Company. All rights reserved.
  • Page 7: Plug Stem Pinning

    H. Insert two or three pieces of packing (17) into the packing box to assist in guiding the stem and plug during lapping. Figure 6 © 2015 General Electric Company. All rights reserved. Masoneilan 10000 Series Globe Valve Instruction Manual | 4...
  • Page 8: Packing Box

    Lubricants are available through your GE Representative or District Office. Replacement of the packing (17) is accomplished in the Note: The pin must be recessed approximately 1/16" below the same manner as the standard lubricator box.
  • Page 9: Valve Body Reassembly

    ANSI Class Size (in) ft. lbs. m.daN ¾ ½-13 ½-13 1½ ½-13 ½-13 ¾-10 ¾-10 ¾-10 ¾-10 1½-8 1¼-8 789 (1) It is extremely important to tighten stud nuts evenly and in the sequence shown otherwise damage to the guides or bushings could occur. © 2015 General Electric Company. All rights reserved. Masoneilan 10000 Series Globe Valve Instruction Manual | 6...
  • Page 10 Lantern Ring (Optional) Packing Follower Figure 9 Note: V-Port is shown 90° out of position. It must be installed as explained in Section 3. Figure 10 7 | GE Oil & Gas © 2015 General Electric Company. All rights reserved.
  • Page 11 Notes © 2015 General Electric Company. All rights reserved. Masoneilan 10000 Series Globe Valve Instruction Manual | 8...
  • Page 12 DISTRIBUTOR E.P. & S. - FRANCE 24 bis rue de Picpus 75012 PARIS Tel: +33 (0)9 83 01 21 01 ventes@fr-eps.com E.P. & S. - CAMEROON Immeuble Carré d'Or, Rue Njo-Njo Bonapriso, DOUALA Tel: +237 6 52 12 70 95 ventes@fr-eps.com Visit our web-site: www.fr-eps.com...

Table of Contents