eRRU Quick Installation Guide
In this document, eRRU3232 is used as an example. Difference in
installation and operation of other eRRU products are also described
eRRU Installation Modes
a
Common Requirements
CAUTION
• In all scenarios, the eRRU must be installed vertically.
• Do not stand the eRRU upright because the load-bearing capacity of the RF ports at the bottom of the eRRU is low.
• Place a foam pad or cardboard on the ground to protect the housing of the eRRU from damage before the binding.
b
Installing the eRRU on a Pole
Normal pole
推荐抱杆直径值为80mm
c
Installing the Mounting Kits on the Wall
NOTE
• For a single RRU, the wall can bear four
times of the weight of an RRU.
• Expansion bolts must be tightened to 30 N· m
to ensure that the bolts work properly and the
wall remains intact without cracks in it.
mm
Special pole
0
eRRU Installation Process
NOTE
Before installing the RRU, check the RRU and
accessories based on the equipment packing list and
ensure that all materials are complete.
Start
Unpack and Inspect the
Equipment
Install eRRUs on a
pole (slides 4 and
5)
Install RRU cables (slides 8
to 13)
Check the hardware
installation (slides 13 and 14)
Conduct power-on check
(slide 14)
End
V100R005C00 02
.
Install eRRUs on
the wall (slide 6)