hit counter script

Power-On Sequence For Switch Stacks; Installing The Switch; Rack Mounting - Cisco Catalyst 2960 Installation Manual

Hide thumbs Also See for Catalyst 2960:
Table of Contents

Advertisement

Installing the Switch

Power-On Sequence for Switch Stacks

Consider these guidelines before you power on the switches in a stack:
For conditions that can cause a stack master re-election or to manually elect the stack master, see the
"Managing Switch Stacks" chapter in the switch software configuration guide on Cisco.com.
Installing the Switch
Rack-Mounting
Installation in other than 19-inch racks requires a bracket kit not included with the switch.
shows the standard 19-inch brackets and ETSI mounting brackets. You can order the ETSI bracket from
your Cisco sales representative:700-19781XX
Warning
To prevent bodily injury when mounting or servicing this unit in a rack, you must take special
precautions to ensure that the system remains stable. The following guidelines are provided to ensure
your safety:
- This unit should be mounted at the bottom of the rack if it is the only unit in the rack.
- When mounting this unit in a partially filled rack, load the rack from the bottom to the top with the heaviest
component at the bottom of the rack.
- If the rack is provided with stabilizing devices, install the stabilizers before mounting or servicing the unit in
the rack. Statement 1006
Catalyst 2960-S Switch Hardware Installation Guide
1-10
The sequence in which the switches are first powered on might affect the switch that becomes the
stack master.
If you want a particular switch to be the stack master, power on that switch first. This switch
becomes the stack master and remains the stack master until a master re-election. After 2 minutes,
power on the other stack switches.
If you have no preference as to which switch becomes the stack master, power on all the switches in
the stack within a 1-minute timeframe. These switches participate in the stack master election.
Switches powered on after the 1-minute timeframe do not participate in the election.
Power off a switch before you add it to or remove it from an existing switch stack.
Rack-Mounting, page 1-10
Wall-Mounting, page 1-14
Table- or Shelf-Mounting, page 1-17
After Switch Installation, page 1-17
Chapter 1
Switch Installation
Figure 1-10
OL-19732-04