Testing precautions
Once the fitting is permanently connected to the
mains supply, a commissioning discharge test as
required in AS/NZS 2293.2 must be carried out.
You will need to allow 24 hours for the battery to
fully charge prior to conducting this test,
presently (at the time of writing), the standard
requires that fittings operate in emergency mode
for a period not less than 2 hours for their
commissioning test and for not less than 90
minutes thereafter (it is required that 6 monthly
discharge tests be carried out). You will need to
keep the records for the commissioning test and
enter them into the building emergency services
logbook or via other recording methods as
allowed by AS/NZS 2293.2.
Troubleshooting guide
If you have installed and connected the fitting as per the instructions listed earlier and it does
not function correctly, use the following table as a guide to fixing the problem. Look up the
type of fault in the left column and check the possible causes from the right column.
If the fitting still does not work after checking these possible causes, contact ABB customer
service in Australia on 1800 60 20 20.
No. Fault
1
LED lamp and indicator LED not lit
2
LED lamp not lit but red indicator is lit
3
LED lamp not lit but indicator LED is flashing green
4
LED lamp is lit but red indicator LED not lit
5
The LED lamp does not switch to emergency mode
when the test button is pressed
6
Indicator LED is constant green
7
Indicator LED not red after commissioning
8
The LED lamp works momentarily on emergency
when the test button is pressed
ABB Australia Pty Limited
For enquiries
ABB contact centre: 1800 60 20 20
E-mail: AU-ABB-Stanilite@abb.com
www.stanilite.com.au
Construction sites
Continuously switching off the mains power
supply that is connected to emergency light
fittings during the construction phase of an
installation will cause these fittings to discharge
and charge their batteries many times over a
short period; this can shorten life of the battery.
ABB does not recommend such practices and
may not honour the warranty on batteries when
they are subjected to such harsh operating
conditions. Emergency light fittings are designed
to be discharge tested once every 6 months as
per AS/NZS 2293.2, subjecting the product to
repeated discharge or charge cycles is regarded
as an abuse of the fittings.
Possible causes
AC supply not connected; or
AC supply turned off
LED lamp damaged; or
LED lamp plug incorrectly inserted in the mother board
LED lamp damaged; or
LED lamp plug incorrectly inserted in the mother board
LED damaged; or
Check battery connection
Test switch damaged
Test switch damaged; or
Self check fail - return to factory
Check battery connection and battery plug polarity
Battery not yet charged (allow up to 24 hours)
© Copyright 2020 ABB. All rights reserved.
I N S TA L L AT I O N M A N U A L
Stanilite®
Platinum exit LED edgelit recessed
DALI emergency
Thank you for choosing ABB product
Please read this document thoroughly before
commencing installation and retain for future
reference. Contact ABB customer service in
Australia on 1800 60 20 20 if you need any
assistance. The installation instructions were
correct at the time of print. To reflect changes in
technology and Australian standards; ABB
reserves the right to amend the instructions
without notice. Updated document can be found
on the Stanilite website.
Safety warning
In Australia and New Zealand, only licensed
electricians are permitted by law to work with
240 volt electrical installations.
Do not attempt to install or connect this product
unless you are a licensed electrician.
Turn off and isolate the electrical supply before
connecting this fitting to the building wires.
Do not touch the terminals of the terminal block
when the light fitting is energised.
The only user-serviceable part is the battery
pack. LED light source is not user-serviceable.
Do not attempt to service other parts of the
fitting as this will void the warranty.
As the installer, it is your responsibility to ensure
compliance with all relevant building and safety
codes, (ie: AS/NZS 3000, AS/NZS 2293). Refer to
the applicable standards for data and mains
cabling installation procedures and
requirements.
This document covers
What's inside the box
Safety warning
Recessed base assembly
Installation instructions
Diffuser assembly
Removal instructions
Ceiling cut-out template
Testing precautions
Picto diffuser insert pack
Troubleshooting guide
Mains power cord
Installation manual
Warranty information
Recessed luminaire classification for this product
is CA90 (ref. AS/NZS 60598.2.2-2016)
Note: Not suitable for use with loose-fill
insulation.
No fire rated box is required for the product.
Important to note:
• This product is designed for indoor use only.
DALI (Digital Addressable Lighting Interface)
DALI is widely acknowledged as being an open
protocol as defined under IEC 62386 and is
designed only for communication in lighting
systems.
ABB exit and emergency luminaire with DALI
functionality comply with DALI standard IEC
62386.
The DALI edgelit recessed wiring consists of
additional 2 control wires apart from the active
and neutral wires (4 cores) power cord supplied
with product.
Note: No mains or mains carrying cables are to
be connected to DALI terminals or 2 control
wires (white and black).
Doc no. 29-01162_1

Advertisement

loading

Summary of Contents for ABB Stanilite DALI emergency

  • Page 1 Thank you for choosing ABB product Warranty information Please read this document thoroughly before If the fitting still does not work after checking these possible causes, contact ABB customer commencing installation and retain for future service in Australia on 1800 60 20 20.
  • Page 2 Installation instructions 3. Install the pictograph inserts by sliding into the diffuser. The pictograph inserts can be installed in Note: The circuit supplying mains power to the fitting must not be energised until installation of the diffuser prior to installing the diffuser assembly in the fitting. Fitting is supplied standard the fitting is completed.