  • Page 1 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual...
  • Page 3: Table Of Contents

    1MRS757275 COM600 series, version 4.1 Issued: 30.06.2011 IEC 61850 Proxy Server User's Manual Version: C/13.3.2015 Contents: About this manual .................. 5 1.1. Copyright ..................5 1.2. Disclaimer ..................5 1.3. Conformity ..................6 1.4. Trademarks ..................6 1.5. General ..................6 1.6.
  • Page 4 COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual 4.1. About this section ................. 33 4.2. Activating COM600 with new configurations ....... 33 4.3. Diagnostics .................. 33 4.3.1. IEC 61850 Proxy Server OPC Client ......33 4.3.1.1. Online diagnostics ........33 4.3.1.2.
  • Page 5: About This Manual

    Copyright This document and parts thereof must not be reproduced or copied without written per- mission from ABB, and the contents thereof must not be imparted to a third party, nor used for any unauthorized purpose. The software or hardware described in this document is furnished under a license and may be used, copied, or disclosed only in accordance with the terms of such license.
  • Page 6: Conformity

    (EMC Directive 2004/108/EC) and concerning electrical equipment for use within specified voltage limits (Low-voltage directive 2006/95/EC). This conformity is the result of tests conducted by ABB in accordance with the product standards EN 50263 and EN 60255-26 for the EMC directive, and with the product standards EN 60255-1 and EN 60255-27 for the low voltage directive.
  • Page 7: Document Conventions

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual Operation This section covers the basic operation procedures you can carry out when transferring or activating Grid Automation Controller COM600 (later referred to as COM600) with new configurations. You are also given instructions on how to monitor and control the IEC 61850 Proxy Server OPC Client.
  • Page 8: Use Of Symbols

    COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual 1.7. Use of symbols This publication includes warning, caution, and information icons that point out safety- related conditions or other important information. It also includes tip icons to point out useful information to the reader.
  • Page 9: Abbreviations

    A communication protocol developed by Echelon. LON Application Guideline for A proprietary method of ABB on top of the standard LON pro- substation automation; LAG tocol. Series of standards specifications aiming at open connectivity in industrial automation and the enterprise systems that support industry.
  • Page 10 COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual Abbreviation Description ASDU Application Service Data Unit BRCB Buffered Report Control Block Data Access DMCD Data Message Code Definition Data Object Gateway, component connecting two communication networks together Human Machine Interface International Electrotechnical Commission Intelligent Electronic Device LON Application Guideline for substation automation...
  • Page 11: Related Documents

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual 1.10. Related documents Name of the manual MRS number COM600 User's manual 1MRS756125 1.11. Document revisions Document version/date Product revision History A/30.6.2011 Document created B/31.5.2012 Document revised C/13.3.2015 Document revised...
  • Page 12: Introduction

    The COM600 series 4.1 release comprises of the following products: • COM600S – COM600 for substation automation(for IEC and ANSI markets) • COM600S is a substation automation and data management unit that integrates devices, facilitates operations and manages communication in utility or industrial distribution substations. •...
  • Page 13: Functional Overview

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual 2.2. Functional overview IEC61850_Proxy_Server_Functional_Overview.PNG Figure 2.2-1 Functional overview of IEC 61850 Proxy Server IEC 61850 Proxy Server enables IEC 61850-8-1 MMS clients to access data and services of COM600. It also features a GOOSE send functionality for publishing data. With these features, it is possible to connect non-IEC61850 IEDs to the IEC 61850 network via COM600.
  • Page 14: Iec 61850 Proxy Server Features

    COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual for the IEC 61850 Proxy Server are initiated by IEC 61850 service request from an IEC 61850 client or by data updates from the connected OPC servers. 2.3. IEC 61850 Proxy Server features The IEC 61850 Proxy Server supports the following features: •...
  • Page 15: Configuration

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual Configuration 3.1. About this section This section guides you in the configuration tasks required before you can start using the IEC 61850 Proxy Server. For information on the IEC 61850 data modeling, refer to COM600 User's Manual.
  • Page 16 COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual When configuring OPC servers the following characters cannot be used in object names: \ ` ' ' #. Also avoid using a space in object names. overview_PROXY.png Figure 3.2-1 Example view of SAB600 communication structure The configuration work can be divided into two separate tasks: 1.
  • Page 17: Building Object Tree

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual 3.3. Building object tree 3.3.1. General about building object tree The object tree is built in the Communication structure of SAB600, see Figure 3.2-1. It is built by adding objects in a logical order starting from the OPC Server object. Before the IEC 61850 Proxy Server can be taken into use, you need to configure an OPC server for the process communication.
  • Page 18: Iec 61850 Data Publishing

    COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual 2. Select the check-boxes in the first column to add LDs to the IEC61850 Proxy Server OPC Client configuration. 3. Click Apply to create the configuration with the selected IEDs to the communication structure.
  • Page 19 1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual The data set can be modified with the Dataset Editor. Open the Dataset Editor by right- clicking the Dataset object and selecting Dataset Editor. The Dataset object has a set of data attributes: •...
  • Page 20: Data Reporting

    COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual </DO> </LNClass> </Dataset> The data set identifies the data set to be created. LNClass and DO are used to determine which LN/DOs should be added to the dataset. For example: <DataSet name="StatNrml">...
  • Page 21 1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual There are buffered and unbuffered report control blocks: • In a Buffered Report Control Block (BRCB) internal events issue immediate sending of reports, or buffer the events for transmission. This way the values of a data object are not lost due to transport flow control constraints or loss of connection.
  • Page 22 COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual Property/Parameter Value or value range/Default Description Buffered True Controls if the RCB is buffered or unbuffered. False Default: True Configuration Revision 0...2147483647 Configuration revision of the data set referenced by this RCB.
  • Page 23 1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual Property/Parameter Value or value range/Default Description Data Set True Data Set False Default: False Entry ID True Entry ID False Default: True Reason Code True Reason Code False Default: True Sequence Number True Sequence Number...
  • Page 24: Configuring Reporting

    COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual 3.4.4. Configuring reporting Reporting is preconfigured automatically. Data sets for necessary data are created and linked to configured report control blocks. To configure reporting: 1. Create and configure a Data Set object. creating_dataset Figure 3.4.4-1 Creating a new data set 2.
  • Page 25: Goose Messaging

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual ReportClient Figure 3.4.4-3 Adding ReportClient objects 4. Configure the report control block. 5. Configure the data set of the report control block. data_set_properties Figure 3.4.4-4 Data set properties 3.4.5. GOOSE messaging The generic object oriented substation event (GOOSE) is used in substation automation for fast horizontal communication between IEDs.
  • Page 26 COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual IEC61850 Proxy Server supports sending of GOOSE messages. The receiving of GOOSE messages is handled by the IEC 61850 OPC Server. The GOOSE data is sent periodically in 802.1Q multicast frames over the local network. When data changes, the GOOSE frame is sent several times in a fast cycle to prevent data losses.
  • Page 27: Configuring Goose Publishing

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual 3.4.6. Configuring GOOSE publishing To send GOOSE data, you must first define the sending data set used by the GOOSE control block and then create the control block. 1. Create a new Data Set. Rename it if you plan to use several different sets of data (see 3.4.2.1, Dataset Editor).
  • Page 28 COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual modifying_dataset.png Figure 3.4.6-2 Modifying the data set to be sent with GOOSE 3. Create a new GOOSE Control Block (GoCB). creating_gcb.png Figure 3.4.6-3 Creating GOOSE Control Block 4. Configure the GOOSE control block, see Figure 3.4.6-4. •...
  • Page 29: Configuring Objects

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual GOOSE_control_block_properties Figure 3.4.6-4 GOOSE Control Block properties 3.5. Configuring objects 3.5.1. General about configuring objects After the objects have been added, configure the object properties. Figure 3.5.1-1 shows an example of how to use SAB600 to configure the object properties for IEC 61850 Proxy Server OPC Client.
  • Page 30: Configuring Iec 61850 Proxy Server Opc Client

    Table 3.5.2-1 IEC 61850 Proxy Server OPC Client properties Property / Value or Value range/ Default Description Parameter Basic AE Prog ID ABB.IEC61850_Slave_OPC_AE_Server.Instance[1] ProgID for OPC Alarm and Event Server. (not configurable) DA Prog ID ABB.IEC61850_Slave_OPC_DA.Instance[1] ProgID for OPC Data Access Server. (not configurable) 3.5.3.
  • Page 31: Configuring Iec 61850 Proxy Ied

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual Table 3.5.3-1 IEC 61850 Proxy Subnetwork properties Property / Para- Value or Value range/ Default Description meter Communication Port Communication Port ETH0 LAN port used by the IEC 61850 protocol used for GOOSE sending.
  • Page 32: Configuring Iec 61850 Proxy Device Properties

    COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual 3.5.5. Configuring IEC 61850 Proxy Device properties IEC 61850 Proxy Device does not have any configurable properties. 3.6. Exporting configuration to other systems When IEC 61850 Proxy configuration is finalized from the COM600 point of view, configuration needs to be exported from the IEC 61850 Proxy IED level using the CID Export function.
  • Page 33: Operation

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual Operation 4.1. About this section This section describes the basic operation procedures you can carry out after the IEC 61850 Proxy Server object properties have been configured. After this, you can, for example, monitor and control the condition of connections in the Proxy Subnetwork.
  • Page 34: Diagnostic Ae Client

    COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual Proxy_online_diagnostics.png Figure 4.3.1.1-1 IEC 61850 Proxy Server Online diagnostics In Online diagnostics dialog box you can: • reset the IEC 61850 Proxy Server OPC Client • view the event log file •...
  • Page 35: Iec 61850 Proxy Ied

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual Proxy_diagnostic_AE_client.png Figure 4.3.1.2-1 IEC 61850 Proxy Server Diagnostic AE client 4.3.2. IEC 61850 Proxy IED 4.3.3. Online diagnostics The IEC 61850 communication activity can be monitored with the Online diagnostics function, see Figure 4.3.3-1: •...
  • Page 36 COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual IED_online_diagnostics.png Figure 4.3.3-1 IEC 61850 Proxy IED online diagnostics...
  • Page 37: Technical Reference

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual Technical reference 5.1. ASCI conformance statement 5.1.1. ACSI conformance statement ACSI conformance statements shall be used to provide an overview and details about a device claiming conformance with ACSI: •...
  • Page 38: Acsi Models Conformance Statement

    COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual c1 – shall be ‘M’ if support for LOGICAL-DEVICE model has been declared. O – Optional M – Mandatory 5.1.3. ACSI models conformance statement Table 5.1.3-1 ACSI models conformance statement Client/Sub- Server/Pub- Value/Comments...
  • Page 39: Acsi Service Conformance Statement

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual Client/Sub- Server/Pub- Value/Comments scriber lisher M8-6 BufTm M8-7 IntgPd M8-8 M8-9 conf-revision Logging Log control M9-1 IntgPd Control SUPPORTED If GSE (B31/32) is supported GOOSE SUPPORTED (send) GSSE If SVC (41/42) is supported Multicast SVC Unicast SVC Time...
  • Page 40 COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual Table 5.1.4-1 ACSI service Conformance statement Services Client/Sub- Server/Pub- Value/Comments TP/MC scriber lisher Server ServerDirectory SUPPORTED Application association Associate SUPPORTED Abort SUPPORTED Release SUPPORTED Logical device LogicalDeviceDirectory SUPPORTED Logical node LogicalNodeDirectory SUPPORTED GetAllDataValues...
  • Page 41 1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual Services Client/Sub- Server/Pub- Value/Comments TP/MC scriber lisher Buffered report control block (BRCB) Report SUPPORTED S24-1 data-change (dchg) S24-2 qchg-change (qchg) S24-3 data-update (dupd) GetBRCBValues SUPPORTED SetBRCBValues SUPPORTED Unbuffered report control block (URCB) Report SUPPORTED...
  • Page 42 COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual Services Client/Sub- Server/Pub- Value/Comments TP/MC scriber lisher GetGSSEElementNumber GetGsCBValues SetGsCBValues Transmission of sampled value model (SVC) Multicast SVC SendMSVMessage GetMSVCBValues SetMSVCBValues Unicast SVC SendUSVMessage GetUSVCBValues SetMSVCBValues Control Select SUPPORTED SelectWithValue SUPPORTED Cancel...
  • Page 43: Scl Conformance

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual Services Client/Sub- Server/Pub- Value/Comments TP/MC scriber lisher supported TimeStamp resol- (nearest negative ution power of 2 in seconds) c6 – shall declare support for at least one (BRCB or URCB). c7 –...
  • Page 44: Mms Conformance

    COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual Table 5.3.1-1 PICS for A-Profile support Client Server Value/Comment Client/Server A-Profile SUPPORTED GOOSE/GSE Management SUPPORTED A-Profle GSSE A-Profile TimeSync A-Profile c1 – shall be ‘m’ if support for any service specified for Client/S are declared within the ACSI basic conformance statement.
  • Page 45 1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual All required IEC 61850 services for supporting the ACSI services stated to be supported are supported by the used MMS stack MMS-EASE Light.
  • Page 47: Index

    1MRS757275 COM600 series, version 4.1 IEC 61850 Proxy Server User's Manual Index ACSI conformance ....................37 basic conformance ..................37 models conformance ..................38 service conformance ..................39 adding IEC 61850 Proxy Server OPC Client ..............17 building object tree ....................17 IEC 61850 Proxy Server OPC Client ..............
  • Page 48 COM600 series, version 4.1 1MRS757275 IEC 61850 Proxy Server User's Manual IEC 61850 Proxy Server ..................30 features ......................14 IEC 61850 Proxy Server OPC Client adding ......................17 object configuring ..................... 29 online diagnostics ..................33, 35 Proxy Configuration Tool ..................17 report control block .....................
  • Page 50 Contact us ABB Oy Distribution Automation P.O. Box 699 FI-65101 VAASA, FINLAND Tel. +358 10 22 11 Fax. +358 10 224 1094 ABB Inc. Distribution Automation 655 Century Point Lake Mary, FL 32746, USA Tel: +1 407 732 2000 Fax: +1 407 732 2335...